CAREER HISTORY
Jacobs, Project
Engineer (Sizewell B) 16/06/2008 –
07/08/2008
Contract
for Main Feedwater Flowmeters
- Detail
to follow
- Detail
to follow
Alstec,
C&I Engineer (Sizewell B) 14/04/2008
– 12/05/2008
Contract
for Seawater Pump Refit and Commissioning
- As
Sole C&I Technician responsible for all testing and calibration of
instruments on the refurbished seawater pump, gearbox and 11Kv motor.
- Supported
commissioning and testing of the pump including faultfinding and override
modifications to allow uncoupled motor testing.
Alstec,
C&I Engineer (Sizewell B) 15/03/2008
– 11/04/2008
Contract for
Refuelling Outage
- Responsible
for a team of 7 C&I technicians to undertake the general C&I outage
work, including planning, setting to work, resolving problems and spares
issues.
- Carried
out the functional impact testing of the primary reactor loose parts system,
including accelerometer replacement on the reactor vessel head
Alstec,
C&I Engineer (Sizewell B) 3/12/2007
– 21/12/2007
Contract for New
Building Hook-Up
- Responsible
for a team of electricians, overseeing the wiring of services to new
buildings on site and in the training facility. Including Telephone and
network connections, PA system and fire system links.
- Organising
the supply and terminations of two Fibre optic cables to link the new
building to the site/company Network.
Alstec,
C&I Technician (Sizewell B) 12/11/2007
– 1/12/2007
Contract for Radwaste
improvements
- Low
level waste drum storage camera replacement project. Replaced 9 cameras and
associated power supply boxes and junction boxes.
- Panel
modifications to allow the use of LCD monitors, and a new control joystick.
Alstec,
C&I Technician (Sizewell B) 17/09/2007
– 9/11/2007
Contract for Radwaste
improvements
- Carried
out modification to optical sensors, which are used as part of a PLC based
Encapsulation system for radioactive resin, including relay wiring and PLC
inputs.
- Full
commissioning and system testing. Drawing revisions, and document closeout.
Alstec,
C&I Engineer (Sizewell B) 18/06/2007
– 06/07/2007
Contract for Work
Order Card Review
- Full
and in depth review (in advance of the forthcoming Refuelling outage) of the
work order card instructions, Maintenance procedures and technical drawings
- Reporting
the findings of all problems to relevant engineers and support personnel,
and writing an in depth report on each jobs location to assist contractors
in outage.
Alstec,
Commissioning Engineer (Calder Hall) 08/01/2007
– 29/03/2007
Contract to commission
de-fuelling machines
- Commissioning
newly installed equipment as part of a mayor overhaul of the de-fuelling
systems on site, in preparation for de-fuelling and decommissioning.
- Full
testing of hydraulic manipulator arm, variable speed drive for fuel delivery
system and flask movement carriage.
Alstec,
Instrument Technician (Sizewell B) 23/10/2006 – 22/12/2006
Contract for Seawater
Pump Refit and Commissioning
- As
Sole C&I Technician responsible for all testing and calibration of
instruments on the refurbished seawater pump, gearbox and 11Kv motor.
- Supported
commissioning and testing of the pump including faultfinding and override
modifications to allow uncoupled motor testing.
Alstec,
Instrument Engineer (Sizewell B) 28/08/2006 – 20/10/2006
Contract for
Refuelling Outage
- Responsible
for a team of 7 C&I technicians to undertake the general C&I outage
work, including planning, setting to work, resolving problems and spares
issues.
- Carried
out the functional impact testing of the primary reactor loose parts system,
including accelerometer replacement on the reactor vessel head
Alstec,
Instrument Engineer (Dungeness B) 26/04/2006
– 29/07/2006
Contract for Gas
Circulator Outage
- Supervise
a team of C&I technicians and electricians to undertake the Gas
Circulator outage. Including setting to work, risk assessment and resolution
of identified problems and spares issues.
- Attended
progress meetings and leased with other projects to maintain the outage
timetable.
Alstec,
Instrument Technician (Sizewell A) 05/09/2005
– 26/04/2006
Contract for Active Waste Facility
refurbish
- Responsible
for testing/commissioning of newly installed transmitters and level systems.
- Configuring
SCADA inputs and checking outstations and network connections. Also alarm
system upgrades from relay based to Rochester system.
Alstec,
Instrument Technician (Sizewell B) 20/06/2005
– 31/08/2005
Contract for Seawater
Pump Refit and Commissioning
- As
Sole C&I Technician responsible for all testing and calibration of
instruments on the refurbished seawater pump, gearbox and 11Kv motor.
- Supported
commissioning and testing of the pump including faultfinding and override
modifications to allow uncoupled motor testing.
Alstec,
Instrument Technician (Sizewell A)
03/05/2005 – 27/05/2005
Contact
Active waste facility.
- Checking
all drawings for “As built” status, and amending the drawings as
required.
- Repairs
to Active areas Remote Camera.
Alstec,
Electrical Supervisor
19/04/2005 – 28/04/2005
Contract for Lost blade project (Wylfa
nuclear power station, Magnox)
- Review
drawings for applicability.
- Set
up and assisted with the heat soak testing of a full Vibration Monitoring
panel.
Alstec (FMA), Air Operated Valves Facilitator 14/03/2005
– 17/04/2005
Contract
for Sizewell B Refuelling Outage
- As
a nominated Supervisor, setting teams to work, and ensuring everything is
ready to complete the work, including Scaffolding, Lagging removed, Tools,
and parts. And when required liasing with other teams to resolve identified
problems.
- Assist
contactor partners in plant identification and welfare problems.
Alstec,
Instrument Technician (Sizewell A, Magnox)
07/03/2005 – 11/03/2005
Contract for refuelling machine depth
indicator decoder cable separation.
- Carrying
out modifications to the cabling to cure an identified fault in the depth
indicator. This included installing a new cable and junction box.
Alstec,
Electrical Supervisor
17/01/2005 – 20/02/2005
Contract for Flask Filling Manipulator
(Wylfa nuclear power station, Magnox)
- Electrical
Supervisor, supervising electricians carrying out the installation of a new
hydraulic manipulator control desk, and rectifying discrepancies in drawings
and Quality plans. Also updating plans and drawings as required.
- Holding
Electrical and radiological safety documents, and liasing with required
groups to ensure the program kept moving, and was completed to time.
Alstec,
Instrument Technician
07/12/2004 – 15/12/2004
Contract for Heysham 1, Active Facility
Modification
- Modifications
to Norlog Chassis to correct non-conforming Nuclear Safety related
electrical interlocks.
- Testing
the Irradiated fuel handling system to confirm correct operation of the
safety systems.
Lorne Stewart,
Instrument Technician 04/10/2004 –
29/10/2004
Contract for Merck Sharp Dohme (Hoddesdon)
- General
checking of installed instruments and quality control on new pharmaceutical
plant.
- Completing
paper work for installation and loop checks ECT.
Alstec,
Instrument Technician
20/09/2004 – 01/10/2004
Contract for Sizewell
B, Loose Parts System Upgrade.
- The
complete strip down and installation of a new loose parts system, designed
to detect and record failed fuel elements or loose parts in the reactor.
- Full
Rewiring and commissioning.
Alstec,
Instrument Technician
30/08/2004 – 16/09/2004
Contract for Sizewell
B, Work Order Card walk downs.
- Complete
Review of work scope for the next Refuelling outage. Including plant
walk-downs to confirm requirements for each task in the work scope.
- Liasing
with engineers and stores to identify the correct parts required, and
specialist tool used.
Alstec,
Instrument Technician
14/06/2004 – 28/07/2004
Contract
for Sizewell A Refuelling modifications R2
Alstec,
Instrument Technician
05/04/2003 – 08/05/2004
Contract for Sizewell A Flask Bay door
project.
- Carrying
out modifications to the flask doors, changing them from roller doors to
hydraulically operated doors. New wiring and control circuits installed.
- Assisted
in the commissioning and testing of the doors.
Alstec,
Instrument Technician
19/11/2003 – 24/01/2004
Contract for Sizewell A Refuelling
modifications R1
- Carrying
out modifications to refuelling machine operation desk. Including complete
desk refurbishment and new panel installation, all wiring and assisting
commissioning.
- Fitting
and wiring a new Inverter and associated control boxes, to the refuelling
machine, checking wiring to fuel grab hook and CCTV equipment.
Alstec,
Instrument Technician
01/10/2003 - 10/11/2003
Contract for Sizewell B Refuelling Outage
- Part of a small team
Carrying out general instrument calibrations, including pneumatic valve
testing and set up, pressure transmitters and switches.
- Assisted Framatome,
Liasing with the planning and operation departments, and carrying out valve
and level troll calibrations.
|